Corporate Entry|Türkçe|Site Map
Gas Gensets / kVA - kVA / TJ275DW-NG5A
   Power Output Ratings
    50 Hz 60 Hz
 Standby Power (ESP) kVA 273 X
kW 218 X
 Prime Power (PRP) kVA 246 X
kW 197 X

   Engine
    50 Hz 60 Hz
 Manufacturer   DOOSAN
 Origin   KOREA
 Model   GV158TIR
 No of Cylinder / Configuration   8 - V TYPE
 Displacement lt 14,618
 Bore / Stroke mm 128 / 142
 Compression Ratio   10,5:1
 Aspiration   Turbocharged and Intercooled(Water to Air)
 Governor Type   ELECTRONIC
 Cooling System   WATER
 Coolant Capacity lt 192,3
 Lubrication Oil Capacity lt 31
 Electrical System VDC 24
 Speed / Frequency   1500 rpm / 50 Hz X
 Engine Gross Power kWm 253 X
 Fuel Consumption (Nm³/h) 110 % 63,2 X
100 % 58,4 X
75 % 48,2 X
50 % 39 X
 Exhaust Outlet Temperature °C 495 X
 Exhaust Gas Flow m³/min 30 X
 Combustion Air Flow m³/min 18,5 X
 Cooling Air Flow m³/min 550 X

   Alternator
    50 Hz 60 Hz
 Manufacturer   MARELLI
 Origin   ITALY
 Model   MJB315SA4
 Power Factor   0,8
 No of Phase   3
 No of Bearing   SINGLE
 No of Poles   4
 No of Leads   12
 Voltage Regulation ( Steady State)   ± %0,5
 Insulation Class   H
 Degree of Protection   IP 23
 Excitation System   AVR (Automatic Voltage Regulator), Brushless
 Connection Type   STAR
 Total Harmonic Content (No Load) % THD < %2
 Frequency Hz 50 60
 Voltage Output VAC 230 / 400 X
 Rated Power (Standby) kVA 330 X
 Efficiency % 93,1 X

   Dimensions
  W x L x H (mm) Weight (kg) Fuel Tank (lt)
 Canopied 1650 x 4500 x 2350 3200 N/A
 Open Skid 1650 x 3500 x 1850 2450 N/A
Standby Power
Standby power is defined as the maximum power available during a variable electrical power sequence, under the stated operating conditions, for which a generating set is capable of delivering in the event of a utility power outage or under test conditions for up to 500 hours of operation per year under average of 70% load. Overloading is not permissible.
Prime Power
Prime power is defined as being the maximum power which a generating set is capable of delivering continuously whilst supplying a variable electrical load. Average load should be 70%. The generator can be overloaded 10% for 1 hour per 12 hours.